Chatter Latest Posts
Street & Utility Improvements Project Update
by Jeff Steinborn - 12/01/23 02:55 PM
Annual Audubon Christmas Bird Count
by Jeff Steinborn - 11/28/23 10:59 AM
Scanning Bird Feeders Pays Off With Personal Rewar
by Jeff Steinborn - 11/21/23 02:56 PM
Centennial Lutheran Church Advent Event 11/30
by Jeff Steinborn - 11/15/23 03:30 PM
Autumn Lingers With Unexpected Sightings Galore
by Jeff Steinborn - 11/08/23 11:39 AM
Henderson Feathers Photos
Annual Audubon Christmas Bird Count
Annual Audubon Christmas Bird Count
by Jeff Steinborn, November 28
Scanning Bird Feeders Pays Off With Personal Rewar
Autumn Lingers With Unexpected Sightings Galore
Autumn Lingers With Unexpected Sightings Galore
by Jeff Steinborn, November 8
December
S M T W T F S
1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31
Who's Online Now
0 members (), 32 guests, and 2 robots.
Key: Admin, Global Mod, Mod
Previous Thread
Next Thread
Print Thread
Rate Thread
Page 1 of 2 1 2
Joined: Jan 2004
Posts: 6,973
Chatter Elite
OP Online Content
Chatter Elite
Joined: Jan 2004
Posts: 6,973
This week the contractor will begin this week by moving in Traffic Control Signs, installing temporary erosion control items, and removing trees in preparation for the construction of some storm sewer and culverts. Tree removal operations, may block traffic on South St (Phase 1) at times. Next week (week of October 2nd), the contractor plans to mill the roadway on each phase slated for construction this fall. Once milled, they will lay the millings back down, roll, and pack so that it is similar to a gravel roadway.

[Linked Image from i.imgur.com]

Joined: Jan 2004
Posts: 6,973
Chatter Elite
OP Online Content
Chatter Elite
Joined: Jan 2004
Posts: 6,973
Project Update:
Contractor to Televise Sanitary Sewer Monday (10/2). They will then reclaim the road surface on Tuesday (10/3). South St will then be closed beginning Wednesday (10/4) to put in a crossing culvert.

[Linked Image from i.imgur.com]

Joined: Jan 2004
Posts: 6,973
Chatter Elite
OP Online Content
Chatter Elite
Joined: Jan 2004
Posts: 6,973
[Linked Image from i.imgur.com]

[Linked Image from i.imgur.com]

Joined: Jan 2004
Posts: 6,973
Chatter Elite
OP Online Content
Chatter Elite
Joined: Jan 2004
Posts: 6,973
Hjerpe Contracting will be working on Minnesota St today (10/10) installing sanitary sewer and water main. All traffic is detoured to South St. A temporary access has been constructed for residents living on 7th St S to get around construction at the intersection of Minnesota and 7th St S.

Joined: Jan 2004
Posts: 6,973
Chatter Elite
OP Online Content
Chatter Elite
Joined: Jan 2004
Posts: 6,973
Next week, the contractor will continue sanitary sewer installation along 8th St S and on Minnesota St (from 8th St S to 9th St S). It is also anticipated that the following week (10/23) the drilling sub-contractor will beginning drilling work on 9th St S (from just south of W Ridge Blvd to Minnesota St). The detour route will remain unchanged as traffic will be able to traverse around the drill rig machine while its working. Please contact me if you have any questions regarding where the detour route is or where to park to access your property.

Thanks,
Douglas J. Scott, PE (MN)
Project Engineer
Short Elliott Hendrickson Inc. (SEH®)
507.237.8384 direct | 507.317.8847 mobile | 651.490.2000 main

[Linked Image from i.imgur.com]

[Linked Image from i.imgur.com]

Joined: Jan 2004
Posts: 6,973
Chatter Elite
OP Online Content
Chatter Elite
Joined: Jan 2004
Posts: 6,973
Today (10/20) Hjerpe Contracting will be continuing to reconstruct sanitary sewer main on 8th St S. Next week, sanitary sewer work will continue on Minnesota St and 9th St S. Also next week, Watermain work will also take place on Minnesota St (from 7th St S to 8th St S) and will include a connection to the system where pressure in the mains will be decreased to ensure safe working conditions for the connection. See Project Update #6 for more details.

Thanks,
Douglas J. Scott, PE (MN)
Project Engineer
Short Elliott Hendrickson Inc. (SEH®)
507.237.8384 direct | 507.317.8847 mobile | 651.490.2000 main

[Linked Image from i.imgur.com]

Joined: Jan 2004
Posts: 6,973
Chatter Elite
OP Online Content
Chatter Elite
Joined: Jan 2004
Posts: 6,973
[Linked Image from i.imgur.com]

Joined: Jan 2004
Posts: 6,973
Chatter Elite
OP Online Content
Chatter Elite
Joined: Jan 2004
Posts: 6,973
[Linked Image from i.imgur.com]

Joined: Jan 2004
Posts: 6,973
Chatter Elite
OP Online Content
Chatter Elite
Joined: Jan 2004
Posts: 6,973
Hjerpe Contracting is continuing to work on services along Minnesota St (between 8th St S and 9th St S) and 9th St S. Another crew is working on storm sewer followed by sub cutting and rebuilding the streets. This will continue into next week. See project update for more information.

Thanks,
Douglas J. Scott, PE (MN)
Project Engineer
Short Elliott Hendrickson Inc. (SEH®)
507.237.8384 direct | 507.317.8847 mobile | 651.490.2000 main

[Linked Image from i.imgur.com]

Joined: Jan 2004
Posts: 6,973
Chatter Elite
OP Online Content
Chatter Elite
Joined: Jan 2004
Posts: 6,973
Contractor will throttle down pressure today to make live connections to the water distribution system. Contractor to install storm sewer, sub cut, and re build 9th St (from W Ridge Rd to Minnesota St), Maple St. and Minnesota St. Contractor does not plan on working Thursday of Friday next week due to the Thanksgiving Holiday. See Project Update #10 for more information.

Douglas J. Scott, PE (MN)
Project Engineer
Short Elliott Hendrickson Inc. (SEH®)
507.237.8384 direct | 507.317.8847 mobile | 651.490.2000 main

[Linked Image from i.imgur.com]

Page 1 of 2 1 2

Moderated by  Jeff Steinborn 

Link Copied to Clipboard
Follow us on Facebook!
ShoutChat
Comment Guidelines: Do post respectful and insightful comments. Don't flame, hate, spam.
Popular Topics(Views)
4,211,265 Vikings Talk
1,074,765 Twins Talk
283,605 Kraut Shirt & I
275,028 College Hockey
197,573 College Hockey
181,411 Smoking Ban
Powered by UBB.threads™ PHP Forum Software 7.7.5
(Release build 20201027)
Responsive Width:

PHP: 7.4.33 Page Time: 0.009s Queries: 36 (0.004s) Memory: 3.4298 MB (Peak: 3.5172 MB) Data Comp: Off Server Time: 2023-12-02 02:13:42 UTC
Valid HTML 5 and Valid CSS