The contractor will complete sanitary sewer main construction on 4th Street N today. On Monday, sanitary sewer stubs will be extended to the east side of the 4th Street N. The first pipe crew will then continue with construction of sanitary sewer main on Market Street to the east. The second pipe crew will complete sanitary sewer installation on 3rd Street S today, south of the levee. Work on Minnesota Street will be started as well. After completion of sanitary sewer main on 3rd Street S and Minnesota Street, the crews will go back to complete sanitary sewer service replacements.